Carscreugh Renewable Energy Park

18 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines18
Installed capacity15.3 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)John Laing Environmental Assets Group/ REG Power Management
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2001 2003 2005 2007 2009 2011 2013 2015 Project timeline Permission expired May 2000 Application submitted May 2006 Permission granted May 2011 Under construction June 2013 Operational January 2014

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4501.

What the register tells us

The application was determined in about 60 months. Construction to first power took about 7 months. A planning permission on this site expired in May 2000. The scheme has been operating for about 12 years. That works out at 0.85 MW per turbine on average.