Altamuskin Extension

3 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines3
Installed capacity7.1 MW
Turbine capacity2.35 MW
Tip height110 m
Operator (or applicant)Altamuskin Windfarm (Energia)
Turbine manufacturerEnercon
Turbine modelE-92

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2007 2009 2011 2013 2015 2017 2019 2021 Scheme REPD 4139 Application submitted February 2006 Permission granted December 2008 Under construction March 2016 Operational March 2017 Scheme REPD 4557 Application submitted April 2011 Permission granted January 2015 Under construction March 2016 Operational March 2017 Permission expired January 2020

From application to operation, this scheme took about 11 years.

The register links a second scheme on this site (REPD ref 4557, Operational): 3 turbines · 2.35 MW each · 110 m tip height · applicant Altamuskin Windfarm (Energia). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4139.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 12 months. The scheme has been operating for about 9 years. That works out at 2.37 MW per turbine on average.

Nearby

See all wind farms in Co. Tyrone.