Barrow

30 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines30
Installed capacity90 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Orsted (formerly Dong Energy)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 Project timeline Application submitted May 2002 Permission granted March 2003 Under construction May 2005 Operational April 2006

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2546.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 11 months. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 3 MW per turbine on average.