Blaengwen

10 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines10
Installed capacity23 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Statkraft and Catamount Energy Corporation
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 Project timeline Application submitted July 2006 Permission granted March 2007 Permission expired March 2007 Under construction November 2008 Operational November 2009

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4670.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 12 months. A planning permission on this site expired in March 2007. The scheme has been operating for about 17 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Dyfed.