Blary Hill Wind Farm

14 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines14
Installed capacity35 MW
Turbine capacity2.5 MW
Tip height110 m
Operator (or applicant)Renewables Infrastructure Group / Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Project timeline Application submitted August 2014 Refused April 2015 Permission granted June 2017 Granted on appeal June 2017 Under construction May 2020 Permission expired June 2020 Operational January 2022

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4605.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 20 months. The register records a refusal in April 2015 before the scheme progressed. Permission was ultimately granted on appeal in June 2017. A planning permission on this site expired in June 2020. The scheme has been operating for about 4 years. That works out at 2.5 MW per turbine on average.