3 turbines · operational · Fife
| Status | Operational |
|---|---|
| County / region | Fife |
| Turbines | 3 |
| Installed capacity | 1.5 MW |
| Turbine capacity | 0.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Messrs Stevenson, Watson and Brunton |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
The register links a second scheme on this site (REPD ref 3847, Revised): 3 turbines · 0.9 MW each · applicant Messrs Stevenson, Watson and Brunton. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3370.
The application was determined in about 10 months. Construction to first power took about 10 months. A planning permission on this site expired in May 2011. The scheme has been operating for about 12 years. That works out at 0.5 MW per turbine on average.