Brockholes Wind Cluster

3 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines3
Installed capacity2.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Brockholes Farm
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted April 2009 Permission granted May 2010 Under construction February 2012 Operational February 2013 Permission expired May 2014

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2672.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 12 months. A planning permission on this site expired in May 2014. The scheme has been operating for about 13 years. That works out at 0.8 MW per turbine on average.

Nearby

See all wind farms in Borders.