6 turbines · operational · Powys
| Status | Operational |
|---|---|
| County / region | Powys |
| Turbines | 6 |
| Installed capacity | 13.8 MW |
| Turbine capacity | 2.3 MW |
| Tip height | 100 m |
| Operator (or applicant) | Njord Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2873.
The application was determined in about 20 months. Construction to first power took about 19 months. Permission was ultimately granted on appeal in August 2016. A planning permission on this site expired in August 2014. The scheme has been operating for about 7 years. That works out at 2.3 MW per turbine on average.