Castlecraig

10 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines10
Installed capacity25 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted December 2006 Permission granted June 2011 Under construction April 2017 Operational August 2018

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4112.

What the register tells us

The application was determined in about 54 months. Construction to first power took about 16 months. The scheme has been operating for about 8 years. That works out at 2.5 MW per turbine on average.