Centrica (Lincs)

75 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines75
Installed capacity270 MW
Turbine capacity3.6 MW
Tip heightnot recorded
Operator (or applicant)�rsted
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-3.6-120

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted January 2007 Permission granted October 2008 Under construction March 2010 Operational July 2013 Permission expired October 2014

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2513.

What the register tells us

The application was determined in about 21 months. Construction to first power took about 40 months. A planning permission on this site expired in October 2014. The scheme has been operating for about 13 years. That works out at 3.6 MW per turbine on average.