Crighshane

14 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines14
Installed capacity32.2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Greencoat (formerly Energia Renewables)
Turbine manufacturerEnercon
Turbine modelE70

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2005 2007 2009 2011 2013 2015 2017 2019 Scheme REPD 4041 Application submitted December 2004 Permission granted June 2007 Under construction May 2011 Operational June 2012 Permission expired June 2013 Scheme REPD 4562 Application submitted March 2011 Refused September 2019

From application to operation, this scheme took about 8 years.

The register links a second scheme on this site (REPD ref 4562, Application Refused): 6 turbines · 2.5 MW each · applicant DW consultancy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4041.

What the register tells us

The application was determined in about 30 months. Construction to first power took about 13 months. A planning permission on this site expired in June 2013. The scheme has been operating for about 14 years. That works out at 2.3 MW per turbine on average.