Crockbaravally Wind Farm

3 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines3
Installed capacity7.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Golden Square Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted January 2009 Permission granted March 2012 Under construction February 2016 Operational February 2017 Permission expired March 2017

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4255.

What the register tells us

The application was determined in about 38 months. Construction to first power took about 12 months. A planning permission on this site expired in March 2017. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.