Crystal Rig Wind Farm Phase IV

11 turbines · under construction · Borders

Wind farm facts

StatusUnder Construction
County / regionBorders
Turbines11
Installed capacity48 MW
Turbine capacity4 MW
Tip height200 m
Operator (or applicant)Fred Olsen Renewables
Turbine manufacturerSiemens Gamesa
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 Project timeline Application submitted May 2018 Permission granted March 2021 Granted on appeal March 2021 Under construction August 2024 Permission expired March 2027

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4631.

What the register tells us

The application was determined in about 34 months. Permission was ultimately granted on appeal in March 2021. A planning permission on this site expired in March 2027. That works out at 4.36 MW per turbine on average.