Curraghamulkin (Dooish Wind Farm)

10 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines10
Installed capacity30 MW
Turbine capacity3 MW
Tip height130 m
Operator (or applicant)DW Consultancy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted March 2008 Permission expired November 2012 Refused January 2016 Permission granted November 2017 Granted on appeal November 2017 Under construction January 2018 Operational July 2018

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4151.

What the register tells us

The application was determined in about 116 months. Construction to first power took about 6 months. The register records a refusal in January 2016 before the scheme progressed. Permission was ultimately granted on appeal in November 2017. A planning permission on this site expired in November 2012. The scheme has been operating for about 8 years. That works out at 3 MW per turbine on average.