Drumduff

3 turbines · operational · Lothian

Wind farm facts

StatusOperational
County / regionLothian
Turbines3
Installed capacity8.5 MW
Turbine capacity2.83 MW
Tip heightnot recorded
Operator (or applicant)Green Breeze Energy Ltd
Turbine manufacturerVestas
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted February 2014 Permission granted June 2015 Under construction January 2017 Operational July 2017 Permission expired June 2018

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4218.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 6 months. A planning permission on this site expired in June 2018. The scheme has been operating for about 9 years. That works out at 2.83 MW per turbine on average.