Dudgeon East

67 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines67
Installed capacity402 MW
Turbine capacity6 MW
Tip heightnot recorded
Operator (or applicant)Statoil / Statkraft
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-6.0-154

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted June 2009 Permission granted July 2012 Permission expired July 2012 Under construction March 2016 Operational October 2017

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2538.

What the register tells us

The application was determined in about 37 months. Construction to first power took about 19 months. A planning permission on this site expired in July 2012. The scheme has been operating for about 9 years. That works out at 6 MW per turbine on average.