67 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 67 |
| Installed capacity | 402 MW |
| Turbine capacity | 6 MW |
| Tip height | not recorded |
| Operator (or applicant) | Statoil / Statkraft |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-6.0-154 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2538.
The application was determined in about 37 months. Construction to first power took about 19 months. A planning permission on this site expired in July 2012. The scheme has been operating for about 9 years. That works out at 6 MW per turbine on average.