Dun Law

26 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines26
Installed capacity17.2 MW
Turbine capacity0.66 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturerVestas
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 Original scheme Application submitted May 1996 Permission granted July 1997 Operational August 2000 Later scheme Application submitted April 2005 Permission granted January 2006 Under construction May 2009 Operational September 2009

From application to operation, this scheme took about 4 years.

The register links a second scheme on this site (REPD ref 3579, Operational): 35 turbines · 0.85 MW each · applicant Renewable Energy Systems (RES). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3570.

What the register tells us

The application was determined in about 14 months. The scheme has been operating for about 26 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.66 MW per turbine on average.