8 turbines · operational · Fife
| Status | Operational |
|---|---|
| County / region | Fife |
| Turbines | 8 |
| Installed capacity | 18.4 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | The Renewables Infrastructure Group (TRIG) |
| Turbine manufacturer | Vestas |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4363.
The application was determined in about 18 months. Construction to first power took about 9 months. A planning permission on this site expired in March 2011. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Fife.