Eastman Chemicals, Workington

2 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Unknown
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted June 2003 Permission granted September 2003 Under construction August 2006 Operational October 2006 Permission expired September 2014

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2935.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 2 months. A planning permission on this site expired in September 2014. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.