Eshmore

3 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines3
Installed capacity6.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Energia Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2007 2009 2011 2013 2015 2017 2019 2021 Scheme REPD 4111 Application submitted October 2006 Permission granted October 2011 Under construction January 2016 Permission expired October 2016 Operational December 2016 Scheme REPD 5861 Application submitted July 2015 Permission granted July 2016 Permission expired July 2021

From application to operation, this scheme took about 10 years.

The register links a second scheme on this site (REPD ref 5861, Planning Permission Expired): 1 turbines · 2.3 MW each · 103 m tip height · applicant Energia Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4111.

What the register tells us

The application was determined in about 60 months. Construction to first power took about 11 months. A planning permission on this site expired in October 2016. The scheme has been operating for about 10 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Co. Tyrone.