3 turbines · operational · Co. Tyrone
| Status | Operational |
|---|---|
| County / region | Co. Tyrone |
| Turbines | 3 |
| Installed capacity | 6.9 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Energia Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
The register links a second scheme on this site (REPD ref 5861, Planning Permission Expired): 1 turbines · 2.3 MW each · 103 m tip height · applicant Energia Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4111.
The application was determined in about 60 months. Construction to first power took about 11 months. A planning permission on this site expired in October 2016. The scheme has been operating for about 10 years. That works out at 2.3 MW per turbine on average.