Furness Wind Farm/High Winds (Harlock Repowering)

5 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines5
Installed capacity11.5 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Baywind Co-op & Energy4All & Belltown Power
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Permission expired July 2011 Application submitted September 2011 Refused May 2013 Permission granted July 2014 Granted on appeal July 2014 Under construction December 2015 Operational November 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4177.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 11 months. The register records a refusal in May 2013 before the scheme progressed. Permission was ultimately granted on appeal in July 2014. A planning permission on this site expired in July 2011. The scheme has been operating for about 10 years. That works out at 2.3 MW per turbine on average.