Galloper Wind Farm

56 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines56
Installed capacity353 MW
Turbine capacity6.3 MW
Tip heightnot recorded
Operator (or applicant)RWE Npower Renewables
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-6.0-154

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted November 2011 Permission granted May 2013 Under construction July 2016 Operational March 2018

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2526.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 20 months. The scheme has been operating for about 8 years. That works out at 6.3 MW per turbine on average.