Glengesh Lower Forest (Murley)

9 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines9
Installed capacity20.7 MW
Turbine capacity2.3 MW
Tip height127 m
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 Project timeline Application submitted October 2015 Permission granted May 2018 Permission expired May 2023 Operational July 2024

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6096.

What the register tells us

The application was determined in about 31 months. A planning permission on this site expired in May 2023. The scheme has been operating for about 2 years. That works out at 2.3 MW per turbine on average.