Glenkerie Wind Farm

11 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines11
Installed capacity22 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Novera Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Original scheme Application submitted December 2007 Permission granted September 2008 Permission expired September 2010 Under construction April 2011 Operational February 2012 Later scheme Application submitted May 2013 Refused December 2014 Permission granted July 2015 Granted on appeal July 2015 Permission expired July 2018

From application to operation, this scheme took about 5 years.

The register links a second scheme on this site (REPD ref 4578, Planning Permission Expired): 6 turbines · 2.5 MW each · applicant Muirhall Energy (formerly Infinis). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3538.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 10 months. A planning permission on this site expired in September 2010. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.