30 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 30 |
| Installed capacity | 108 MW |
| Turbine capacity | 3.6 MW |
| Tip height | not recorded |
| Operator (or applicant) | Orsted (formerly Dong Energy) |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-3.6-107 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2490.
The application was determined in about 24 months. Construction to first power took about 3 months. The scheme has been operating for about 17 years. That works out at 3.6 MW per turbine on average.