Hendy Wind Farm

7 turbines · under construction · Powys

Wind farm facts

StatusUnder Construction
County / regionPowys
Turbines7
Installed capacity14.4 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Njord Energy Ltd
Turbine manufacturerVestas
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 2020 2021 Project timeline Application submitted July 2014 Refused May 2017 Permission granted October 2018 Granted on appeal October 2018 Under construction July 2020

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4377.

What the register tells us

The application was determined in about 51 months. The register records a refusal in May 2017 before the scheme progressed. Permission was ultimately granted on appeal in October 2018. That works out at 2.06 MW per turbine on average.