Humber Gateway A

73 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines73
Installed capacity219 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)E.ON Humber Wind Ltd/ Balfour Beatty Investments and Equitix.
Turbine manufacturerVestas
Turbine modelV112-3.0

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted April 2008 Permission expired February 2010 Permission granted February 2011 Under construction August 2013 Operational May 2015

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2544.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 21 months. A planning permission on this site expired in February 2010. The scheme has been operating for about 11 years. That works out at 3 MW per turbine on average.