73 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 73 |
| Installed capacity | 219 MW |
| Turbine capacity | 3 MW |
| Tip height | not recorded |
| Operator (or applicant) | E.ON Humber Wind Ltd/ Balfour Beatty Investments and Equitix. |
| Turbine manufacturer | Vestas |
| Turbine model | V112-3.0 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2544.
The application was determined in about 34 months. Construction to first power took about 21 months. A planning permission on this site expired in February 2010. The scheme has been operating for about 11 years. That works out at 3 MW per turbine on average.
See all wind farms in Offshore.