5 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 5 |
| Installed capacity | 30 MW |
| Turbine capacity | 6 MW |
| Tip height | not recorded |
| Operator (or applicant) | Statoil |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SWT-6.0-154 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2479.
The application was determined in about 7 months. Construction to first power took about 6 months. A planning permission on this site expired in October 2017. The scheme has been operating for about 9 years. That works out at 6 MW per turbine on average.