Inch Cape

72 turbines · under construction · Offshore

Wind farm facts

StatusUnder Construction
County / regionOffshore
Turbines72
Installed capacity1080 MW
Turbine capacity15 MW
Tip height291 m
Operator (or applicant)Red Rock Power (ICOL)
Turbine manufacturerVestas
Turbine modelV236-15.0

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Project timeline Application submitted July 2013 Permission granted May 2017 Under construction June 2025

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2527.

What the register tells us

The application was determined in about 46 months. That works out at 15 MW per turbine on average.