72 turbines · under construction · Offshore
| Status | Under Construction |
|---|---|
| County / region | Offshore |
| Turbines | 72 |
| Installed capacity | 1080 MW |
| Turbine capacity | 15 MW |
| Tip height | 291 m |
| Operator (or applicant) | Red Rock Power (ICOL) |
| Turbine manufacturer | Vestas |
| Turbine model | V236-15.0 |
Vestas · V236-15.0 · 72 turbines · 15 MW each · rotor 236 m
Source: Wikipedia, wind farm article, 2026, read on 2026-09-19. Corroborated by 3 further sources. Where OpenStreetMap tags differ, this record prevails.
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
DevelopmentConstructionOperationAhead (repowering horizon at 22 years)
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2527.
The application was determined in about 46 months. That works out at 15 MW per turbine on average.
See all wind farms in Offshore.
| Data | Source | Extract |
|---|---|---|
| Site, capacity, status, planning milestones | Renewable Energy Planning Database (DESNZ, Open Government Licence v3) | Q2 2026, published 03/08/2026 |
| Turbine positions | OpenStreetMap contributors (ODbL) | 19/08/2026 |
| Manufacturer and model | OpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong. | 19/08/2026 |
Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.