Inner Dowsing

27 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines27
Installed capacity97.2 MW
Turbine capacity3.6 MW
Tip heightnot recorded
Operator (or applicant)XceCo
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-3.7-107

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted September 2002 Permission granted September 2003 Under construction March 2008 Operational April 2008 Permission expired September 2011

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2491.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 1 month. A planning permission on this site expired in September 2011. The scheme has been operating for about 18 years. That works out at 3.6 MW per turbine on average.