Kelburn

14 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines14
Installed capacity28 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted July 2004 Refused February 2007 Permission granted August 2009 Granted on appeal August 2009 Under construction November 2010 Operational May 2012

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3149.

What the register tells us

The application was determined in about 61 months. Construction to first power took about 18 months. The register records a refusal in February 2007 before the scheme progressed. Permission was ultimately granted on appeal in August 2009. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.