14 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 14 |
| Installed capacity | 28 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Renewable Energy Systems (RES) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3149.
The application was determined in about 61 months. Construction to first power took about 18 months. The register records a refusal in February 2007 before the scheme progressed. Permission was ultimately granted on appeal in August 2009. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.