Kentish Flats

30 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines30
Installed capacity90 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Vattenfall
Turbine manufacturerVestas
Turbine modelV90-3.0

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted August 2002 Permission granted March 2003 Under construction June 2004 Operational September 2005 Permission expired March 2015

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2492.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 15 months. A planning permission on this site expired in March 2015. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 3 MW per turbine on average.