6 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 6 |
| Installed capacity | 49.5 MW |
| Turbine capacity | 9.5 MW |
| Tip height | 176 m |
| Operator (or applicant) | Grupo Cobra |
| Turbine manufacturer | Vestas |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6136.
The application was determined in about 9 months. Construction to first power took about 36 months. A planning permission on this site expired in March 2016. The scheme has been operating for about 5 years. That works out at 8.25 MW per turbine on average.