12 turbines · operational · Cumbria
| Status | Operational |
|---|---|
| County / region | Cumbria |
| Turbines | 12 |
| Installed capacity | 4.8 MW |
| Turbine capacity | 0.4 MW |
| Tip height | not recorded |
| Operator (or applicant) | Npower Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register links a second scheme on this site (REPD ref 3637, Application Refused): 6 turbines · 3 MW each · 115 m tip height · applicant RWE Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2713.
The application was determined in about 30 months. A planning permission on this site expired in June 2019. The scheme has been operating for about 33 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.4 MW per turbine on average.
See all wind farms in Cumbria.