2 turbines · operational · Dyfed
| Status | Operational |
|---|---|
| County / region | Dyfed |
| Turbines | 2 |
| Installed capacity | 1.6 MW |
| Turbine capacity | 0.8 MW |
| Tip height | not recorded |
| Operator (or applicant) | Wind Energy Direct |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4483.
The application was determined in about 16 months. Construction to first power took about 7 months. The register records a refusal in March 2014 before the scheme progressed. Permission was ultimately granted on appeal in August 2014. The scheme has been operating for about 9 years. That works out at 0.8 MW per turbine on average.
See all wind farms in Dyfed.