Lawrence Landfill

2 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines2
Installed capacity1.6 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Wind Energy Direct
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted April 2013 Refused March 2014 Permission granted August 2014 Granted on appeal August 2014 Under construction August 2016 Operational March 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4483.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 7 months. The register records a refusal in March 2014 before the scheme progressed. Permission was ultimately granted on appeal in August 2014. The scheme has been operating for about 9 years. That works out at 0.8 MW per turbine on average.