Lendrum's Bridge Wind Farm ( Extension 2)

11 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines11
Installed capacity7.3 MW
Turbine capacity0.66 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturerEnercon
Turbine modelE82

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1996 1997 1998 1999 2000 2001 2002 2003 Project timeline Application submitted September 1997 Permission granted May 1998 Operational December 2002

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3566.

What the register tells us

The application was determined in about 8 months. The scheme has been operating for about 24 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.66 MW per turbine on average.