Levenmouth demonstration turbine (Fife Energy Park)

1 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines1
Installed capacity7 MW
Turbine capacity6 MW
Tip heightnot recorded
Operator (or applicant)Catapult
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted December 2009 Permission granted November 2011 Permission expired November 2012 Under construction October 2013 Operational March 2014

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2528.

What the register tells us

The application was determined in about 23 months. Construction to first power took about 5 months. A planning permission on this site expired in November 2012. The scheme has been operating for about 12 years. That works out at 7 MW per turbine on average.