Little Raith Farm

9 turbines · operational · Fife

Wind farm facts

StatusOperational
County / regionFife
Turbines9
Installed capacity25 MW
Turbine capacity2.8 MW
Tip heightnot recorded
Operator (or applicant)Renewables Infrastructure Group
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Original scheme Application submitted December 2004 Permission granted March 2007 Under construction September 2011 Operational November 2012 Later scheme Application submitted July 2014 Refused June 2015

From application to operation, this scheme took about 8 years.

The register links a second scheme on this site (REPD ref 4490, Appeal Refused): 6 turbines · 3 MW each · applicant WK Extension Project Ltd. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4034.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 14 months. The scheme has been operating for about 14 years. That works out at 2.78 MW per turbine on average.