🌊 Offshore wind farm

London Array Phase 1
Offshore

Recorded in WhichWindTurbine: 175 wind turbines in operation. Point the app at one of them to see its profile in real time.

175
turbines
630 MW
MW total
3.6 MW
per turbine

📍 175 turbines mapped — each dot is a turbine recorded in the database. Average position: 51.62787 N · 1.49725 E.

London Array Phase 1

175 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines175
Installed capacity630 MW
Turbine capacity3.6 MW
Tip heightnot recorded
Operator (or applicant)Siemens Gamesa Renewable Energy
Turbine manufacturerSiemens
Turbine modelSWT-3.6-120
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

✓ Verified reference — turbine make and model

Siemens · SWT-3.6-120 · 175 turbines · 3.6 MW each · hub 80 m · rotor 120 m

Source: Tethys (PNNL, U.S. DOE), 2025-05-16, read on 2026-09-14. Corroborated by 1 further source. Where OpenStreetMap tags differ, this record prevails.

✓ Independently confirmed on 2026-09-19 by Generate Energy, “Offshore Wind — East of England” (2025): 175 SWT-3.6-120, 630 MW.

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20352010201520202025today123456
  1. 1Jun 2005 — Application submitted
  2. 2Dec 2006 — Refused
  3. 3Sep 2007 — Permission granted
  4. 4Sep 2007 — Granted on appeal
  5. 5Mar 2011 — Under construction
  6. 6Apr 2013 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2511.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 25 months. The register records a refusal in December 2006 before the scheme progressed. Permission was ultimately granted on appeal in September 2007. The scheme has been operating for about 13 years. That works out at 3.6 MW per turbine on average.

Nearby

See all wind farms in Offshore.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.