Longpark

19 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines19
Installed capacity38 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Wind Prospect
Turbine manufacturerSenvion
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Scheme REPD 3605 Application submitted February 2004 Permission granted August 2005 Under construction June 2009 Operational September 2009 Permission expired August 2016 Scheme REPD 4576 Application submitted April 2014

From application to operation, this scheme took about 5 years.

The register links a second scheme on this site (REPD ref 4576, Application Withdrawn): 5 turbines · 2.5 MW each · 110 m tip height · applicant Wind Prospect. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3605.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 3 months. A planning permission on this site expired in August 2016. The scheme has been operating for about 17 years. That works out at 2 MW per turbine on average.