Lynn

27 turbines · operational · Offshore

Wind farm facts

StatusOperational
County / regionOffshore
Turbines27
Installed capacity97.2 MW
Turbine capacity3.6 MW
Tip heightnot recorded
Operator (or applicant)XceCo
Turbine manufacturerSiemens Gamesa
Turbine modelSWT-3.7-107

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 Project timeline Application submitted October 2003 Permission granted August 2004 Under construction March 2008 Operational March 2008 Permission expired August 2019

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2493.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 0 month. A planning permission on this site expired in August 2019. The scheme has been operating for about 18 years. That works out at 3.6 MW per turbine on average.