Minnygap

15 turbines · revised · Dumfries and Galloway

Wind farm facts

StatusRevised
County / regionDumfries and Galloway
Turbines15
Installed capacity30 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Original scheme Application submitted June 2005 Refused November 2007 Later scheme Application submitted June 2009 Refused October 2012 Permission granted June 2014 Granted on appeal June 2014 Under construction November 2015 Operational March 2017

The register links a second scheme on this site (REPD ref 4437, Operational): 10 turbines · 2.5 MW each · applicant Minnygap (formerly RES). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4521.

What the register tells us

The register records a refusal in November 2007 before the scheme progressed. That works out at 2 MW per turbine on average.