100 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 100 |
| Installed capacity | 950 MW |
| Turbine capacity | 9.5 MW |
| Tip height | 204 m |
| Operator (or applicant) | Diamond Green Limited, CTG & Ocean Winds |
| Turbine manufacturer | Vestas |
| Turbine model | V164-9.5 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2534.
The application was determined in about 19 months. Construction to first power took about 34 months. A planning permission on this site expired in March 2018. The scheme has been operating for about 4 years. That works out at 9.5 MW per turbine on average.