60 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 60 |
| Installed capacity | 882 MW |
| Turbine capacity | 14.7 MW |
| Tip height | 230 m |
| Operator (or applicant) | EDPR |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SG 14-222 DD |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6158.
The application was determined in about 11 months. Construction to first power took about 35 months. A planning permission on this site expired in June 2044. The scheme has been operating for about 1 year. That works out at 14.7 MW per turbine on average.
See all wind farms in Offshore.