Mynydd Clogau Wind Farm

17 turbines · operational · Powys

Wind farm facts

StatusOperational
County / regionPowys
Turbines17
Installed capacity14.5 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Original scheme Application submitted September 1998 Permission granted May 2002 Operational December 2005 Later scheme Application submitted March 2008

From application to operation, this scheme took about 7 years.

The register links a second scheme on this site (REPD ref 3706, Application Withdrawn): 19 turbines · 0.85 MW each · applicant Novera Energy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4684.

What the register tells us

The application was determined in about 44 months. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.85 MW per turbine on average.