54 turbines · operational · Offshore
| Status | Operational |
|---|---|
| County / region | Offshore |
| Turbines | 54 |
| Installed capacity | 450 MW |
| Turbine capacity | 8 MW |
| Tip height | 208 m |
| Operator (or applicant) | EDF Renewables Power |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | SG 8.0-167 DD |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 13 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2522.
The application was determined in about 58 months. Construction to first power took about 66 months. The scheme has been operating for about 1 year. That works out at 8.33 MW per turbine on average.