1 turbines · operational · Fife
| Status | Operational |
|---|---|
| County / region | Fife |
| Turbines | 1 |
| Installed capacity | 1.5 MW |
| Turbine capacity | 1.5 MW |
| Tip height | 127 m |
| Operator (or applicant) | Wind Direct |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4404.
The application was determined in about 6 months. Construction to first power took about 4 months. A planning permission on this site expired in November 2010. The scheme has been operating for about 12 years. That works out at 1.5 MW per turbine on average.
See all wind farms in Fife.